RA Didn’t Meet any of its Road Infrastructure Targets

 

Photo: Nishi Felton

By: Nghinomenwa-vali Hangala 

During the last financial year (FY), the Road Authority has not met any of its infrastructure targets, citing underfunding.

The Road Authority had 6 road infrastructure targets for the year, including the upgrading of roads to bitumen standards, construction of gravel roads, rehabilitation to bitumen standards, resurfacing, and rejuvenation.

These were included in the 2024/25 financial report, which was released by Parliament last week. However, none of them were met, the report summary showed.

For the 2024/25 financial year, the Roads Authority submitted a target-focused funding requirement of N$5.9 billion to the Road Fund Administration (RFA) to implement the planned road maintenance, rehabilitation, upgrading and construction programmes aligned to the approved ISBP. 

However, owing to lower-than-anticipated revenue projections of the RFA, the Authority received an allocation of only N$2.2 billion, representing approximately 37% of the required funding.

In addition, the Authority requested N$2.4 billion from the government (via the State Revenue Fund) to finance ongoing strategic capital road infrastructure projects and the commencement of new social roads projects. 

The approved allocation amounted to N$1.9 billion, representing approximately 78% of the requested funding.

According to the RA, “the continued mismatch between the Authority’s economic optimum annual funding requirements and the actual funding received has significantly constrained the implementation of approved strategic programmes and capital projects.”

Adding that the Authority had to reprioritise projects and optimise the utilisation of the limited resources available.

“Resulting in the deferment or slower implementation of planned interventions,” the report read.

Namibia is contesting to be a logistical hub and a gateway to Africa, with its road infrastructure as key connectors to the port and mainland southern Africa.

It, however, faces steep competition from Tanzania, South Africa, Mozambique and now Angola.

The 2024/25 report shows that only 79.5 km of the targeted 115km was upgraded to bitumen standards (including Low-Volume seals).

Secondly, only 30.06 km of the targeted 50 km construction of gravel roads was achieved.

The Authority also targeted to rehabilitate 132 km of bitumen standard roads during the financial year, but it only managed 5.5 km.

Re-gravelling plans have also suffered, as only 151 km of the targeted 1,200 km was done. 

The Authority explained that the set target was not achieved due to limited funds allocated to the program.

The Authority also targeted to resurface 688 km of the road in 2024/25 FY but only 31.43 km was done.

For resurfacing, the Authority wrote that the target was not achieved due to delayed contract commencements. 

Only deteriorated sections of the road network were carried out.

The RA team indicated in the report that the underfunding has impacted the Authority’s ability to fully achieve the performance targets approved in the ISBP.

Especially those relating to the construction, upgrading, rehabilitation and restoration of the national road network from poor and very poor condition to acceptable service levels.